support@unifiedpapers.com

Develop a work breakdown structure (WBS) from the refined scope statement.

 Management homework help

Attached is the project Charter with feed back from the Instructor.  Please see requirements below.  Build everything based off of the project charter.

Use the following guidelines to complete your assignment:

  • Project scope: Refine the project scope statements from the scope statement in the charter from Week 1.
  • Develop a work breakdown structure (WBS) from the refined scope statement.
  • Project schedule: Using Microsoft® Project and the WBS you developed above, create a schedule for your project’s lifecycle. Include specific tasks and milestones, with time and resource estimates, to meet organizational objectives in 350 words.
  • Project budget: Using Microsoft® Excel® and the project schedule, WBS, and scope statement, create a time-phased budget containing cost estimates. Include direct and indirect costs for labor, machinery, equipment, supplies, and other elements applicable to the project.
  • Project Management (Microsoft Project (WBS))

    1

    8

    Walmart Project: Project Management Charter

    Walmart Project: Project Management Charter

    Being the manager of the project, I’m charged with the task of developing and the transformation of a regular general Walmart store into a Walmart Supercenter, I will develop and build a project charter for the process.

    Project Description Problem

    The proposed project will be a large project that will transform the current Walmart Store into a Walmart Supercenter. We have noticed with great concern that the company needs to expand in terms of merchandise. This can only be accomplished when the company has enough storage square footage for merchandise. We therefore need to build a Walmart Supercenter that will enable the company to attract a pool of customers hence increasing the profit margin and revenues. The new Walmart Supercenter will involve expansion of the current store from a 105,000 square foot building into a 155,000 square foot building. The project is estimate to run for a period of one year and the total cost is budgeted at $7,527,305.

    Result Statement

    After successful completion of the project the company will immensely benefit in terms of increase storage and versatility of available merchandise. With the increase of space, the company will be able to stock and offer diverse products, therefore attracting more customers. Thus, leading to a substantial increase in revenue and profit margin. The image of the company will also be boosted resulting to a competitive advantage against the competitors.

    Project Mission Justification

    The mission of the project will be to build a modern Walmart Supercenter with the ability to store large amounts of merchandise with ability to diversify merchandise sales by use of the company’s revenue, which will be completed in the stipulated time frame (Kerzner, 2017). The new store is supposed to solve the current storage problem and must conform to the current standards of supercenter stores. The cost of the renovation is expected not to deplete the company’s revenue. It should use a reasonable amount of revenue that will not paralyze the company’s operations. Eventually, the project should be completed in the stipulated time to avoid any additional financial and other resource constraints.

    Project Scope Statement

    The main goal of project will be to build a Walmart Supercenter store that will have enough space to store and sale a large number of diverse merchandise. The project objective is to implement the transformation of a general Walmart store into Walmart Supercenter in the time given and use the revenue allocated by the finance department. The project will be estimated to undergo three major phases. The first phase which is projected to run for a period of three months is the ground excavation and foundation building. The project team will hire the earth movers to facilitate the ground excavation for the site where the project will be built. The companies engineer will be given the task of getting the best company to oversee the process.

    The foundation building will be planned for and the team’s mechanical engineer will be mandated to ensure a firm foundation is built. The cost of excavation and building the foundation is estimated to cost about $1,000,000. The second phase of the project is to expand the square footage to 50,000 square feet and it is estimated to take for 4 months. The materials that will be required such as building cement, sand, ballast, building blocks among others will be purchased by the procurement director. The states finest civil mechanical and water engineers will undertake this process (Nicholas & Steyn, 2017), this will cost the company $4,027,000 inclusive of labor and material costs. Final phase of the project will be the roofing, interior design and painting, lasting for a period of two months costing the company $2,500,305 or more dollars.

    The entire stake holders in the project team will be given various tasks to ensure the success of the project. The project manager will ensure that all phases of the project run smoothly by appropriating all the resources required for the project. The finance officer will ensure accountability of the project funds. Project procurement officer will be mandated with purchasing of all the materials. In the team we will also have a risk manager who will assist in forecasting of potential hazards that may affect successful completion of the project.

    Major Deliverables

    The major deliverable of this project will be Site investigation report, Design documents, Engineering report, Proposal, Technical interpretation, Design drawings, Design review Tender document for material suppliers, new equipment or tools, Strategic report, Progress, Usability report. All these deliverables will be very crucial for the expansion of the store.

    High-level Milestones for Significant Events

    Some of high level milestones in this project will be completion of ground excavation to ensure the foundation is initiated. Another milestone will be the issue of certificate to undertake the project from the federal construction authority and city council. The final milestone of the project will be completion of the super center store and start of operations.

    Applicable Technical Requirements

    The major technical requirements for the project is to ensure that the building of the store will be successful which will include the availability of the required building materials, availability of certified architectures and engineers, compliance with the building authorities and city councils and the availability of skilled labor at the construction site.

    Project Constraints

    The transformation of a Walmart Store into a super center store will be faced with constraints such limited number of qualified personnel, accreditation costs. The project might be completed later than the stipulated time causing extra financial costs. Weather and technological dynamics might also affect the completion of the project. Finally, the dollar changes might affect the budgeted cost of the project negatively.

    References

    Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.

    Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Taylor & Francis.

"Get 15% discount on your first 3 orders with us"
Use the following coupon
FIRST15

Order Now

Hi there! Click one of our representatives below and we will get back to you as soon as possible.

Chat with us on WhatsApp