Scenario

As part of the short-term scheduling process, a manager must assign tasks and resources (usually machines and people) to accomplish the job with the objective of minimizing total cost. In this activity, you will use the assignment method to do that.

You work in the production facility that produces widgets. You have four different machines that can produce the same part; however, since each machine is different, the production cost is different. You are responsible for assigning jobs to machines, and you need to make sure to minimize the total cost to produce the widgets.

Calculate the best job assignments based on resources as shown in the following chart.

Costs Machine 1 Machine 2 Machine 3 Machine 4
Widget 1 $9.00 $7.00 $3.00 $5.00
Widget 2 $7.00 $8.00 $12.00 $11.00
Widget 3 $4.00 $6.00 $8.00 $7.00
Widget 4 $6.00 $11.00 $13.00 $10.00

Assignment

Use Excel or the Excel OM Assignment module to calculate the best job assignments based on resources as shown in the chart. After you determine the best job assignment, indicate on your spreadsheet the minimum cost that the company will incur based on this assignment.

"Get 15% discount on your first 3 orders with us"
Use the following coupon
FIRST15

Order Now

Hi there! Click one of our representatives below and we will get back to you as soon as possible.

Chat with us on WhatsApp